Counties / Texas
Foard County power projects
Foard County, Texas has 5 active power projects totalling 1,594 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 984 MW (62%). The largest single project is Big Field Solar (506 MW solar). 1 project has signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
5
1.6 GW capacity
IA signed or later
1
20% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Foard County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Big Field Solar | Solar | 506 | Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B | Screening | 12/31/2029 |
| Seine BESS | BESS | 309 | 60500 Edith Clarke 345kV | IA Signed | 10/01/2027 |
| Montgomery Ranch 2 Wind | Wind | 302 | 60059 Penumbra 345-kV | FIS Requested | 06/02/2030 |
| Pease River Solar | Solar | 276 | Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B | FIS Requested | 06/30/2029 |
| Daisy Solar | Solar | 201 | Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B | FIS Requested | 06/30/2029 |
For residents and landowners
- What power projects are planned in Foard County?
- ERCOT's October 2026 report lists 5 active projects in Foard County totalling 1,594 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.