LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Foard County

Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B

3 active projects totalling 984 MW are queued to connect at Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B in Foard County, Texas, according to ERCOT's October 2026 report.

Active capacity
984 MW
queued at this substation
Active projects
3
3 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
29INR0148Big Field SolarSolar506Screening12/31/20290
28INR0476Pease River SolarSolar276FIS Requested06/30/20290
28INR0535Daisy SolarSolar201FIS Requested06/30/20290