Substation / point of interconnection ยท Foard County
60500 Edith Clarke 345kV
1 active project totalling 309 MW is queued to connect at 60500 Edith Clarke 345kV in Foard County, Texas, according to ERCOT's October 2026 report.
Active capacity
309 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 23INR0140 | Seine BESS | BESS | 309 | IA Signed | 10/01/2027 | 0 |