ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Cooke County power projects

Cooke County, Texas has 5 active power projects totalling 948 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 768 MW (81%). The largest single project is Two Forks BESS (310 MW battery storage). 2 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
5
0.9 GW capacity
IA signed or later
2
40% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026

Changes in Cooke County

COD change
10/01/2026
Two Forks BESS · BESS · Cooke County
Projected COD moved 09/30/2028 → 08/01/2028. Moved earlier.
-2 mo

All projects

ProjectFuelMWSubstationStageCOD
Two Forks BESSBESS310684 SPRING 138kVIA Signed08/01/2028
18-ALPHA BESSBESS307To the 138 kV Valley View Substation, ( Bus No.691)FIS Requested02/01/2028
WILDWINDWind180tap 345kV 1730 KrumW - 2373 AnnaSync Approved04/15/2026
Mountain Springs BESSBESS150704 Mountain Springs 138 kVFIS Approved04/01/2029
Trojan BESS SLFBESS011735 Cedar Elm Switch 345kVFIS Requested07/01/2029

For residents and landowners

What power projects are planned in Cooke County?
ERCOT's October 2026 report lists 5 active projects in Cooke County totalling 948 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.