LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
20INR0033 · Wind · Cooke County

WILDWIND

WILDWIND is a 180 MW wind project in Cooke County, Texas, connecting at tap 345kV 1730 KrumW - 2373 Anna. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 04/15/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
20INR0033
Capacity
180 MW
Fuel
Wind (WT)
Interconnecting entity
Wildcat Creek
Projected COD
04/15/2026
Entered queue
10/18/2017
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/10/2021
    Energization Approved → Sync Approved
  • 12/22/2020
    IA Signed → Energization Approved
  • 02/21/2020
    FIS Approved → IA Signed
  • 11/25/2019
    FIS Requested → FIS Approved
  • 06/14/2018
    Screening → FIS Requested
  • 10/18/2017
    Entered the queue with 180 MW, projected COD 04/15/2026

Other projects at this substation

No other projects at this substation.