Counties / Texas
Collin County power projects
Collin County, Texas has 5 active power projects totalling 975 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 975 MW (100%). The largest single project is Drake BESS (257 MW battery storage). 4 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
5
1.0 GW capacity
IA signed or later
4
80% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Collin County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Drake BESS | BESS | 257 | #833 Wylie Switch 138kV | IA Signed | 01/29/2027 |
| Little Ridge Storage | BESS | 252 | Tap 138kV Swindell (812) - Olinger (818) | FIS Requested | 09/01/2027 |
| Purple Sage BESS 1 | BESS | 156 | Anna 345 kV Bus# 2373. | IA Signed | 02/12/2028 |
| Purple Sage BESS 2 | BESS | 156 | Anna 345 kV Bus# 2373. | IA Signed | 02/12/2028 |
| Bufflehead BESS | BESS | 154 | 2475 Lavon Switch 138kV | IA Signed | 02/15/2027 |
For residents and landowners
- What power projects are planned in Collin County?
- ERCOT's October 2026 report lists 5 active projects in Collin County totalling 975 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.