25INR0101 · BESS · Collin County

Drake BESS

Drake BESS is a 257 MW battery storage project in Collin County, Texas, connecting at #833 Wylie Switch 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 01/29/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0101
Capacity
257 MW
Fuel
BESS (BA)
Interconnecting entity
Mallard Energy Storage LLC
Projected COD
01/29/2027
Entered queue
06/02/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/18/2025
    FIS Requested → FIS Approved
  • 05/06/2025
    FIS Approved → IA Signed
  • 06/17/2022
    Screening → FIS Requested
  • 06/02/2022
    Entered the queue with 257 MW, projected COD 01/29/2027