25INR0238 · BESS · Collin County

Little Ridge Storage

Little Ridge Storage is a 252 MW battery storage project in Collin County, Texas, connecting at Tap 138kV Swindell (812) - Olinger (818). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0238
Capacity
252 MW
Fuel
BESS (BA)
Interconnecting entity
TX BESS B LLC
Projected COD
09/01/2027
Entered queue
04/25/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/25/2023
    Entered the queue with 252 MW, projected COD 09/01/2027
  • 04/25/2023
    Screening → FIS Requested