Counties / Texas
Childress County power projects
Childress County, Texas has 3 active power projects totalling 270 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 170 MW (63%). The largest single project is Fagus Solar Park 3 SLF (170 MW solar). 1 project has signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.
Active projects
3
0.3 GW capacity
IA signed or later
1
33% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
2
since Sep 2026
Changes in Childress County
Withdrawn
Unconfirmed
10/01/2026
Fagus Solar Park 2 SLF · Solar · Childress County
Missing from the latest report, not yet marked withdrawn by ERCOT. Still queued at 60501 Tesla 345 kV: 170 MW.
−167 MW
Withdrawn
Unconfirmed
10/01/2026
Fagus Solar Park 1 SLF · Solar · Childress County
Missing from the latest report, not yet marked withdrawn by ERCOT. Still queued at 60501 Tesla 345kV: 100 MW.
−166 MW
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Fagus Solar Park 3 SLF | Solar | 170 | 60501 Tesla 345 kV | IA Signed | 06/28/2027 |
| Independence Trail Storage | BESS | 100 | 60501 Tesla 345kV | FIS Requested | 01/01/2028 |
| Fagus Storage SLF | BESS | 0 | 60501 Tesla 345kV | FIS Requested | 09/01/2026 |
| Fagus Solar Park 2 SLF | Solar | 167 | 60501 Tesla 345 kV | Withdrawn | 05/20/2026 |
| Fagus Solar Park 1 SLF | Solar | 166 | 60501 Tesla 345kV | Withdrawn | 05/20/2026 |
For residents and landowners
- What power projects are planned in Childress County?
- ERCOT's October 2026 report lists 3 active projects in Childress County totalling 270 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.