25INR0515 · BESS · Childress County
Fagus Storage SLF
COD date passed
Fagus Storage SLF is a 0 MW battery storage project in Childress County, Texas, connecting at 60501 Tesla 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/01/2026. Its projected COD of 09/01/2026 has already passed without ERCOT approval to synchronize, so the date is likely to move.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0515
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- Substation
- 60501 Tesla 345kV
- County
- Childress County
- Interconnecting entity
- Greenalia Energy Storage MISAE II LLC
- Projected COD
- 09/01/2026
- Entered queue
- 09/22/2023
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/22/2023Entered the queue with 0 MW, projected COD 09/01/2026
- 09/22/2023Screening → FIS Requested
Other projects at this substation
| Fagus Solar Park 1 SLF | Solar | 166 MW | Withdrawn |
| Independence Trail Storage | BESS | 100 MW | FIS Requested |