Counties / Texas
Cherokee County power projects
Cherokee County, Texas has 3 active power projects totalling 1,325 MW in ERCOT's interconnection queue as of the October 2026 report. Natural gas is the largest share at 1,174 MW (89%). The largest single project is Eagle Pines Gas (1,174 MW natural gas). 1 project has signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
3
1.3 GW capacity
IA signed or later
1
33% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Cherokee County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Eagle Pines Gas | Gas | 1,174 | tap 345kV 3109 Stryker - 3123 Trinidad | FIS Requested | 10/30/2028 |
| Rogers Creek BESS | BESS | 100 | Tap 138 KV DailVille (3160) - Neches Pump (3296) | FIS Requested | 04/17/2029 |
| Lumberjack Storage | BESS | 51 | 138 kV Tap 3110 Stryker Creek - 3147 Troup | IA Signed | 11/01/2029 |
For residents and landowners
- What power projects are planned in Cherokee County?
- ERCOT's October 2026 report lists 3 active projects in Cherokee County totalling 1,325 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.