18INR0009 · Gas · Cherokee County
Eagle Pines Gas
Eagle Pines Gas is a 1,174 MW natural gas project in Cherokee County, Texas, connecting at tap 345kV 3109 Stryker - 3123 Trinidad. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 18INR0009
- Capacity
- 1,174 MW
- Fuel
- Gas (CC)
- Substation
- tap 345kV 3109 Stryker - 3123 Trinidad
- County
- Cherokee County
- Interconnecting entity
- FGE Power
- Projected COD
- 10/30/2028
- Entered queue
- 03/30/2015
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/29/2015Screening → FIS Requested
- 03/30/2015Entered the queue with 1,174 MW, projected COD 10/30/2028