25INR0414 · BESS · Cherokee County
Rogers Creek BESS
Rogers Creek BESS is a 100 MW battery storage project in Cherokee County, Texas, connecting at Tap 138 KV DailVille (3160) - Neches Pump (3296). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/17/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0414
- Capacity
- 100 MW
- Fuel
- BESS (BA)
- County
- Cherokee County
- Interconnecting entity
- Dialville BESS
- Projected COD
- 04/17/2029
- Entered queue
- 05/03/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/03/2023Entered the queue with 100 MW, projected COD 04/17/2029
- 05/03/2023Screening → FIS Requested