Counties / Texas
Castro County power projects
Castro County, Texas has 7 active power projects totalling 2,304 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 1,110 MW (48%). The largest single project is Cavell Wind (641 MW wind). 3 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.
Active projects
7
2.3 GW capacity
IA signed or later
3
43% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
1
since Sep 2026
Changes in Castro County
COD change
10/01/2026
Castro Solar · Solar · Castro County
Projected COD moved 09/20/2028 → 04/18/2029. Delay #1 for this project.
+7 mo
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Cavell Wind | Wind | 641 | Tap 345kV 23910 Windmill - 23912 Ogallala Ckt 1 | FIS Requested | 07/30/2029 |
| Cavell Solar | Solar | 502 | Tap 345kV 23910 Windmill - 23912 Ogallala Ckt 1 | FIS Requested | 07/30/2029 |
| Acker BESS | BESS | 301 | 23912 Ogallala 345 kV | IA Signed | 04/17/2029 |
| Ogalalla Storage | BESS | 252 | 23912 OGALLALA_5 345kV | FIS Requested | 04/15/2028 |
| Castro Solar | Solar | 225 | 23912 Ogallala 345kV | IA Signed | 04/18/2029 |
| Nazareth Solar | Solar | 203 | tap 345kV 23914 Tule Canyon - 23912 Ogallala C2 | IA Signed | 08/31/2027 |
| Scarlet Solar | Solar | 180 | tap 345kV 23912 Ogallala - 23910 Windmill | FIS Requested | 08/26/2025 |
| Shifting Gale Wind | Wind | 289 | Not listed | Withdrawn | n/a |
| Hart Wind (Old POI) | Wind | 165 | Not listed | Withdrawn | n/a |
For residents and landowners
- What power projects are planned in Castro County?
- ERCOT's October 2026 report lists 7 active projects in Castro County totalling 2,304 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.