Castro County power projects

Castro County, Texas has 7 active power projects totalling 2,304 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 1,110 MW (48%). The largest single project is Cavell Wind (641 MW wind). 3 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.

Active projects
7
2.3 GW capacity
IA signed or later
3
43% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
1
since Sep 2026

Changes in Castro County

COD change
10/01/2026
Castro Solar · Solar · Castro County
Projected COD moved 09/20/2028 → 04/18/2029. Delay #1 for this project.
+7 mo

All projects

ProjectFuelMWSubstationStageCOD
Cavell WindWind641Tap 345kV 23910 Windmill - 23912 Ogallala Ckt 1FIS Requested07/30/2029
Cavell SolarSolar502Tap 345kV 23910 Windmill - 23912 Ogallala Ckt 1FIS Requested07/30/2029
Acker BESSBESS30123912 Ogallala 345 kVIA Signed04/17/2029
Ogalalla StorageBESS25223912 OGALLALA_5 345kVFIS Requested04/15/2028
Castro SolarSolar22523912 Ogallala 345kVIA Signed04/18/2029
Nazareth SolarSolar203tap 345kV 23914 Tule Canyon - 23912 Ogallala C2IA Signed08/31/2027
Scarlet SolarSolar180tap 345kV 23912 Ogallala - 23910 WindmillFIS Requested08/26/2025
Shifting Gale WindWind289Not listedWithdrawnn/a
Hart Wind (Old POI)Wind165Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Castro County?
ERCOT's October 2026 report lists 7 active projects in Castro County totalling 2,304 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.