19INR0175 · Wind · Castro County
Shifting Gale Wind
Withdrawn
Shifting Gale Wind is a 289 MW wind project in Castro County, Texas, with no point of interconnection listed. It is no longer active in ERCOT's interconnection queue.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 19INR0175
- Capacity
- 289 MW
- Fuel
- Wind
- Substation
- Not listed
- County
- Castro County
- Interconnecting entity
- Not listed
- Projected COD
- n/a
- Entered queue
- 01/28/2025
- ERCOT zone
- n/a
- Size category
- n/a
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/28/2025Listed as inactive