Counties / Texas
Briscoe County power projects
Briscoe County, Texas has 5 active power projects totalling 2,460 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 912 MW (37%). The largest single project is Commodus Wind (641 MW wind). 0 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
5
2.5 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
2
since Sep 2026
Changes in Briscoe County
New
10/01/2026
Black Mountain Briscoe Gas · Gas · Briscoe County
Entered the queue at 23914, Tule Canyon Substation, 345 kV. Projected COD 09/28/2029.
+495 MW
Stage change
09/15/2026
FIS Requested
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Commodus Wind | Wind | 641 | Tap 345kV 23914 Tule Canyon - 23900 Alibates | FIS Requested | 07/30/2029 |
| Commodus Solar | Solar | 502 | Tap 345kV 23914 Tule Canyon - 23900 Alibates | FIS Requested | 07/30/2029 |
| Black Mountain Briscoe Gas | Gas | 495 | 23914, Tule Canyon Substation, 345 kV | FIS Requested | 09/28/2029 |
| BRP Snowdon BESS | BESS | 411 | 23914 Tule Canyon Substation 345kV | FIS Requested | 12/01/2028 |
| Silverton Solar | Solar | 410 | Tap 345kV 23914 Tule Canyon - 79001 Cross_W1 | FIS Requested | 07/01/2029 |
For residents and landowners
- What power projects are planned in Briscoe County?
- ERCOT's October 2026 report lists 5 active projects in Briscoe County totalling 2,460 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.