Substation / point of interconnection · Briscoe County
23914, Tule Canyon Substation, 345 kV
1 active project totalling 495 MW is queued to connect at 23914, Tule Canyon Substation, 345 kV in Briscoe County, Texas, according to ERCOT's October 2026 report.
Active capacity
495 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0397 | Black Mountain Briscoe Gas | Gas | 495 | FIS Requested | 09/28/2029 | 0 |