Angelina County power projects
Angelina County, Texas has 5 active power projects totalling 1,708 MW in ERCOT's interconnection queue as of the October 2026 report. Natural gas is the largest share at 1,200 MW (70%). The largest single project is Longleaf Power Station (600 MW natural gas). 1 project has signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
5
1.7 GW capacity
IA signed or later
1
20% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026
Changes in Angelina County
COD change
10/01/2026
Azalea Springs Solar · Solar · Angelina County
Projected COD moved 07/15/2026 → 11/01/2026. Delay #1 for this project.
+4 mo
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Longleaf Power Station | Gas | 600 | Redland Substation (# 3321) | FIS Requested | 03/31/2029 |
| Longleaf II Power Station | Gas | 600 | 3321 Redland 345 kV | FIS Requested | 07/01/2030 |
| Sun Angel ESS | BESS | 202 | Tap 138kV LUFKINE East (#3326) - HERTY TAP (#3318) | FIS Approved | 09/21/2028 |
| Azalea Springs Solar | Solar | 181 | tap 138kV Jim English – Lufkin Chipper Mill | Sync Approved | 11/01/2026 |
| Solar Star North Herty Storage | BESS | 126 | 3307 Redland Switch 138 kV | FIS Requested | 08/25/2027 |
For residents and landowners
- What power projects are planned in Angelina County?
- ERCOT's October 2026 report lists 5 active projects in Angelina County totalling 1,708 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.