26INR0294 · Gas · Angelina County
Longleaf Power Station
Longleaf Power Station is a 600 MW natural gas project in Angelina County, Texas, connecting at Redland Substation (# 3321). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/31/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0294
- Capacity
- 600 MW
- Fuel
- Gas (GT)
- Substation
- Redland Substation (# 3321)
- County
- Angelina County
- Interconnecting entity
- WattBridge Texas Holdings, LLC
- Projected COD
- 03/31/2029
- Entered queue
- 10/04/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/04/2023Entered the queue with 600 MW, projected COD 03/31/2029
- 10/04/2023Screening → FIS Requested