2 active projects totalling 185 MW are queued to connect at Tap the 138 kV La Pryor (#8008) - Poblano (#8009) in Zavala County, Texas, according to ERCOT's October 2026 report.

Active capacity
185 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0274Flying Kite BessBESS105FIS Requested12/30/20270
25INR0304Flying Kite SolarSolar80IA Signed12/30/20270