Substation / point of interconnection ยท Wilson County
Tap 138kV Eagle Creek (5132) to Floresville (5155)
2 active projects totalling 376 MW are queued to connect at Tap 138kV Eagle Creek (5132) to Floresville (5155) in Wilson County, Texas, according to ERCOT's October 2026 report.
Active capacity
376 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0299 | Moon Stone BESS | BESS | 201 | Screening | 03/31/2029 | 0 |
| 24INR0156 | Moonstone Solar Project | Solar | 175 | IA Signed | 03/31/2029 | 0 |