Substation / point of interconnection · Victoria County
Tap 345kV 80286 DULCE7A - 8676 STATIC7A
3 active projects totalling 2,430 MW are queued to connect at Tap 345kV 80286 DULCE7A - 8676 STATIC7A in Victoria County, Texas, according to ERCOT's October 2026 report.
Active capacity
2,430 MW
queued at this substation
Active projects
3
3 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 33INR0007 | Blue Energy Center - Phase 3 – Steam Stage 2 | Other | 1,320 | FIS Requested | 06/15/2033 | 0 |
| 30INR0150 | Blue Energy Center- Phase 1a - Gas | Gas | 780 | FIS Requested | 05/02/2030 | 0 |
| 29INR0248 | Blue Energy Center - Phase 1b – Steam | Gas | 330 | FIS Requested | 10/17/2031 | 0 |