Substation / point of interconnection ยท Victoria County
8911 BLKBYU4A 138kV
1 active project totalling 155 MW is queued to connect at 8911 BLKBYU4A 138kV in Victoria County, Texas, according to ERCOT's October 2026 report.
Active capacity
155 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0425 | Two Brothers ESS | BESS | 155 | IA Signed | 02/29/2028 | 0 |