Substation / point of interconnection ยท Victoria County
80064 CHOCBAYU4A 138 kV
1 active project totalling 109 MW is queued to connect at 80064 CHOCBAYU4A 138 kV in Victoria County, Texas, according to ERCOT's October 2026 report.
Active capacity
109 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0559 | Georgia-Lynn BESS | BESS | 109 | FIS Requested | 02/20/2028 | 0 |