LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Victoria County

80064 CHOCBAYU4A 138 kV

1 active project totalling 109 MW is queued to connect at 80064 CHOCBAYU4A 138 kV in Victoria County, Texas, according to ERCOT's October 2026 report.

Active capacity
109 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
26INR0559Georgia-Lynn BESSBESS109FIS Requested02/20/20280