Substation / point of interconnection ยท Victoria County
138 kV Loop 463 Substation (#5680)
1 active project totalling 144 MW is queued to connect at 138 kV Loop 463 Substation (#5680) in Victoria County, Texas, according to ERCOT's October 2026 report.
Active capacity
144 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 23INR0342 | Brizo BESS | BESS | 144 | IA Signed | 09/01/2027 | 0 |