Substation / point of interconnection ยท Upton County
tap 345 kV (76000) North McCamey - (59903) Bearkat
2 active projects totalling 581 MW are queued to connect at tap 345 kV (76000) North McCamey - (59903) Bearkat in Upton County, Texas, according to ERCOT's October 2026 report.
Active capacity
581 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0446 | Vista Bluff Wind I "Alternate POI" | Wind | 290 | FIS Requested | 12/31/2029 | 0 |
| 28INR0447 | Vista Bluff Wind II "Alternate POI" | Wind | 290 | FIS Requested | 12/31/2029 | 0 |