10058 Catclaw Switch 138kV

1 active project totalling 420 MW is queued to connect at 10058 Catclaw Switch 138kV in Upton County, Texas, according to ERCOT's October 2026 report.

Active capacity
420 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
28INR0057WindeckerWind420FIS Requested04/17/20280