Substation / point of interconnection ยท Tom Green County
6444 Red Creek 345kV
2 active projects totalling 603 MW are queued to connect at 6444 Red Creek 345kV in Tom Green County, Texas, according to ERCOT's October 2026 report.
Active capacity
603 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0365 | Silver Sky Solar | Solar | 402 | FIS Requested | 12/13/2029 | 0 |
| 29INR0376 | Silver Sky BESS | BESS | 201 | FIS Requested | 12/13/2029 | 0 |