LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
29INR0376 · BESS · Tom Green County

Silver Sky BESS

Silver Sky BESS is a 201 MW battery storage project in Tom Green County, Texas, connecting at 6444 Red Creek 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/13/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0376
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
Lightsource Renewable Energy Development LLC
Projected COD
12/13/2029
Entered queue
08/12/2026
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/12/2026
    Entered the queue with 201 MW, projected COD 12/13/2029
  • 08/12/2026
    Screening → FIS Requested

Other projects at this substation

Silver Sky SolarSolar402 MWFIS Requested