Tapping the 345 kV Double-Circuit Line from Tule Canyon (Bus# 23914) to Alibates (Bus# 23900)
2 active projects totalling 1,144 MW are queued to connect at Tapping the 345 kV Double-Circuit Line from Tule Canyon (Bus# 23914) to Alibates (Bus# 23900) in Swisher County, Texas, according to ERCOT's October 2026 report.
Active capacity
1,144 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0033 | Commodus 2 Wind | Wind | 642 | FIS Requested | 07/30/2029 | 0 |
| 29INR0032 | Commodus 2 Solar | Solar | 502 | FIS Requested | 07/30/2029 | 0 |