Bus#8956 WHITEPOINT 345KV
1 active project totalling 370 MW is queued to connect at Bus#8956 WHITEPOINT 345KV in San Patricio County, Texas, according to ERCOT's October 2026 report.
Active capacity
370 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0496 | Blue Kite | Gas | 370 | FIS Requested | 08/29/2030 | 0 |