28INR0496 · Gas · San Patricio County

Blue Kite

Blue Kite is a 370 MW natural gas project in San Patricio County, Texas, connecting at Bus#8956 WHITEPOINT 345KV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 08/29/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0496
Capacity
370 MW
Fuel
Gas (GT)
Interconnecting entity
RWE Clean Energy Development, LLC
Projected COD
08/29/2030
Entered queue
03/06/2026
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/06/2026
    Entered the queue with 370 MW, projected COD 08/29/2030
  • 03/06/2026
    Screening → FIS Requested