Blue Kite is a 370 MW natural gas project in San Patricio County, Texas, connecting at Bus#8956 WHITEPOINT 345KV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 08/29/2030.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0496
- Capacity
- 370 MW
- Fuel
- Gas (GT)
- Substation
- Bus#8956 WHITEPOINT 345KV
- County
- San Patricio County
- Interconnecting entity
- RWE Clean Energy Development, LLC
- Projected COD
- 08/29/2030
- Entered queue
- 03/06/2026
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/06/2026Entered the queue with 370 MW, projected COD 08/29/2030
- 03/06/2026Screening → FIS Requested