Substation / point of interconnection ยท Runnels County
tap 345kV 1444 BROWN SWITCH - 11406 CENTRAL BLUFF
2 active projects totalling 457 MW are queued to connect at tap 345kV 1444 BROWN SWITCH - 11406 CENTRAL BLUFF in Runnels County, Texas, according to ERCOT's October 2026 report.
Active capacity
457 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0198 | Winters Glow Solar | Solar | 302 | FIS Requested | 04/17/2029 | 0 |
| 28INR0199 | Winters Glow Storage | BESS | 155 | FIS Requested | 04/17/2029 | 0 |