Substation / point of interconnection ยท Pecos County
6671 Tombstone 138kV
1 active project totalling 130 MW is queued to connect at 6671 Tombstone 138kV in Pecos County, Texas, according to ERCOT's October 2026 report.
Active capacity
130 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 22INR0386 | BRP Octans BESS | BESS | 130 | FIS Requested | 12/01/2029 | 0 |