Substation / point of interconnection ยท Pecos County
60400 Lynx 138kV
3 active projects totalling 162 MW are queued to connect at 60400 Lynx 138kV in Pecos County, Texas, according to ERCOT's October 2026 report.
Active capacity
162 MW
queued at this substation
Active projects
3
3 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0287 | Valentine Energy Center | Gas | 162 | FIS Requested | 02/28/2031 | 0 |
| 18INR0079 | Woodward I repower | Wind | 0 | Sync Approved | 12/31/2026 | 0 |
| 18INR0080 | Woodward 2 repower | Wind | 0 | Sync Approved | 12/31/2026 | 0 |