Substation / point of interconnection ยท Pecos County
60152 Fort Stockton Switch 345kV
1 active project totalling 415 MW is queued to connect at 60152 Fort Stockton Switch 345kV in Pecos County, Texas, according to ERCOT's October 2026 report.
Active capacity
415 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0188 | Star Of Texas Solar | Solar | 415 | FIS Requested | 07/01/2029 | 0 |