Substation / point of interconnection ยท Pecos County
38432 TNCENTRY2_1 138 KV
2 active projects totalling 313 MW are queued to connect at 38432 TNCENTRY2_1 138 KV in Pecos County, Texas, according to ERCOT's October 2026 report.
Active capacity
313 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0454 | Longfellow Solar II | Solar | 207 | IA Signed | 12/31/2028 | 0 |
| 24INR0455 | Longfellow BESS II | BESS | 106 | IA Signed | 03/30/2028 | 1 |