ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Pecos County

38430 TNMP White baker Switching Station 138kV

1 active project totalling 77 MW is queued to connect at 38430 TNMP White baker Switching Station 138kV in Pecos County, Texas, according to ERCOT's October 2026 report.

Active capacity
77 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
26INR0296Sherbino II BESS SLFBESS77IA Signed04/19/20270