LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Pecos County

38355 LEON_CRK 138kV

2 active projects totalling 401 MW are queued to connect at 38355 LEON_CRK 138kV in Pecos County, Texas, according to ERCOT's October 2026 report.

Active capacity
401 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0620st gall IIIA StorageBESS201FIS Requested06/01/20280
27INR0621st gall IIIB StorageBESS201FIS Requested06/01/20280