Substation / point of interconnection ยท Pecos County
38355 LEON_CRK 138kV
2 active projects totalling 401 MW are queued to connect at 38355 LEON_CRK 138kV in Pecos County, Texas, according to ERCOT's October 2026 report.
Active capacity
401 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0620 | st gall IIIA Storage | BESS | 201 | FIS Requested | 06/01/2028 | 0 |
| 27INR0621 | st gall IIIB Storage | BESS | 201 | FIS Requested | 06/01/2028 | 0 |