Substation / point of interconnection ยท Nueces County
PRIMAVERA 138kV Substation
1 active project totalling 50 MW is queued to connect at PRIMAVERA 138kV Substation in Nueces County, Texas, according to ERCOT's October 2026 report.
Active capacity
50 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0655 | Lynx Energy Storage_Full | Other | 50 | FIS Requested | 12/01/2027 | 0 |