27INR0655 · Other · Nueces County
Lynx Energy Storage_Full
Lynx Energy Storage_Full is a 50 MW other project in Nueces County, Texas, connecting at PRIMAVERA 138kV Substation. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0655
- Capacity
- 50 MW
- Fuel
- Other (SO)
- Substation
- PRIMAVERA 138kV Substation
- County
- Nueces County
- Interconnecting entity
- Corpus Battery Storage, LLC
- Projected COD
- 12/01/2027
- Entered queue
- 08/06/2026
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Entered the queue with 50 MW, projected COD 12/01/2027
- 09/01/2026Screening → FIS Requested