LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Nolan County

Bus # 1339, Eskota 138kV

1 active project totalling 152 MW is queued to connect at Bus # 1339, Eskota 138kV in Nolan County, Texas, according to ERCOT's October 2026 report.

Active capacity
152 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
28INR0349Jaguarundi Energy StorageBESS152FIS Requested11/10/20290