Jaguarundi Energy Storage
Jaguarundi Energy Storage is a 152 MW battery storage project in Nolan County, Texas, connecting at Bus # 1339, Eskota 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 11/10/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0349
- Capacity
- 152 MW
- Fuel
- BESS (BA)
- Substation
- Bus # 1339, Eskota 138kV
- County
- Nolan County
- Interconnecting entity
- PowerPulse LLC
- Projected COD
- 11/10/2029
- Entered queue
- 06/02/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/02/2025Entered the queue with 152 MW, projected COD 11/10/2029
- 06/02/2025Screening → FIS Requested