Substation / point of interconnection ยท Medina County
Tap 138kV 5813 PearsonSW - 5225 Hondo
1 active project totalling 150 MW is queued to connect at Tap 138kV 5813 PearsonSW - 5225 Hondo in Medina County, Texas, according to ERCOT's October 2026 report.
Active capacity
150 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0203 | Dunlay Solar | Solar | 150 | FIS Requested | 12/31/2030 | 0 |