1 active project totalling 306 MW is queued to connect at Tap 345kV --- KILL_SS_5 (3422) --- BUCK_H_5 (3424) in Lampasas County, Texas, according to ERCOT's October 2026 report.
Active capacity
306 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0277 | Aurora Energy Storage | BESS | 306 | FIS Approved | 09/26/2028 | 0 |