28INR0277 · BESS · Lampasas County
Aurora Energy Storage
Aurora Energy Storage is a 306 MW battery storage project in Lampasas County, Texas, connecting at Tap 345kV --- KILL_SS_5 (3422) --- BUCK_H_5 (3424). ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 09/26/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0277
- Capacity
- 306 MW
- Fuel
- BESS (BA)
- County
- Lampasas County
- Interconnecting entity
- Aurora Energy Storage, LLC
- Projected COD
- 09/26/2028
- Entered queue
- 02/05/2025
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/04/2026FIS Requested → FIS Approved
- 02/05/2025Entered the queue with 306 MW, projected COD 09/26/2028
- 02/05/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.