Substation / point of interconnection ยท Lampasas County
Tap 345kV 3424 BUCKHORN SWITCH - 3422 KILLEEN SWITCH
1 active project totalling 206 MW is queued to connect at Tap 345kV 3424 BUCKHORN SWITCH - 3422 KILLEEN SWITCH in Lampasas County, Texas, according to ERCOT's October 2026 report.
Active capacity
206 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0543 | Thomas Cameron BESS | BESS | 206 | IA Signed | 04/28/2029 | 0 |