LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0543 · BESS · Lampasas County

Thomas Cameron BESS

Thomas Cameron BESS is a 206 MW battery storage project in Lampasas County, Texas, connecting at Tap 345kV 3424 BUCKHORN SWITCH - 3422 KILLEEN SWITCH. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/28/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0543
Capacity
206 MW
Fuel
BESS (BA)
Interconnecting entity
Thomas Cameron BESS LLC
Projected COD
04/28/2029
Entered queue
06/02/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/30/2024
    FIS Approved → IA Signed
  • 07/23/2024
    FIS Requested → FIS Approved
  • 06/02/2023
    Entered the queue with 206 MW, projected COD 04/28/2029
  • 06/02/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.