Substation / point of interconnection · Lamar County

Tap 138 kV Toco Switch (#1700) – Paris Switch (#1693)

2 active projects totalling 223 MW are queued to connect at Tap 138 kV Toco Switch (#1700) – Paris Switch (#1693) in Lamar County, Texas, according to ERCOT's October 2026 report.

Active capacity
223 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
23INR0225MRG GOODY SOLARSolar171Sync Approved08/28/20260
24INR0305MRG Goody StorageBESS52Sync Approved08/28/20260