23INR0225 · Solar · Lamar County
MRG GOODY SOLAR
MRG GOODY SOLAR is a 171 MW solar project in Lamar County, Texas, connecting at Tap 138 kV Toco Switch (#1700) – Paris Switch (#1693). ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 08/28/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0225
- Capacity
- 171 MW
- Fuel
- Solar (PV)
- County
- Lamar County
- Interconnecting entity
- MRG GOODY SOLAR PROJECT, LLC
- Projected COD
- 08/28/2026
- Entered queue
- 03/16/2021
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/27/2026Energization Approved → Sync Approved
- 02/06/2026IA Signed → Energization Approved
- 06/17/2025FIS Requested → FIS Approved
- 11/07/2023FIS Approved → IA Signed
- 03/22/2022Screening → FIS Requested
- 03/16/2021Entered the queue with 171 MW, projected COD 08/28/2026
Other projects at this substation
| MRG Goody Storage | BESS | 52 MW | Sync Approved |