LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0225 · Solar · Lamar County

MRG GOODY SOLAR

MRG GOODY SOLAR is a 171 MW solar project in Lamar County, Texas, connecting at Tap 138 kV Toco Switch (#1700) – Paris Switch (#1693). ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 08/28/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0225
Capacity
171 MW
Fuel
Solar (PV)
Interconnecting entity
MRG GOODY SOLAR PROJECT, LLC
Projected COD
08/28/2026
Entered queue
03/16/2021
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/27/2026
    Energization Approved → Sync Approved
  • 02/06/2026
    IA Signed → Energization Approved
  • 06/17/2025
    FIS Requested → FIS Approved
  • 11/07/2023
    FIS Approved → IA Signed
  • 03/22/2022
    Screening → FIS Requested
  • 03/16/2021
    Entered the queue with 171 MW, projected COD 08/28/2026

Other projects at this substation

MRG Goody StorageBESS52 MWSync Approved